JACKSONVILLE —
Even with the inches of rain falling in December, Pogue construction crews are right on schedule to finish construction on JISD's two new schools in August, Pogue Project Manager Brian Rose said.
“We did have a number of inclement days over December, eight to nine rain days,” Rose said. “That doesn't include muddy days, days where progress may have been slowed or delayed.”
He said although normal production might not have been reached during that time, “on the overall master schedule, we are still scheduled for completion in August.”
Superintendent Dr. Joe Wardell said completing the schools before classes start in the fall 2012 semester is ambitious goal, but it looks like they'll make it.
Wardell said construction on the new Joe Wright and East Side Elementary campuses is between 20 and 25 percent complete.
He said he will be excited to see the end result.
“You spend a lot of time getting your thoughts together on paper, but it's really exciting to see the finished product,” Wardell said. “To see the end result – kids getting out there, it's an exciting process.”
He said to outsiders, it may look like Joe Wright is significantly ahead of East Side construction since the steel framing is up, but that is not the case.
On Joe Wright, the steel may be up, but there's still a lot of foundation work to be accomplished. However, on East Side, the foundation had to come first.
“We poured our last slab on East Side (last week),” Rose said. “That's a big milestone, basically we're out of the dirt now on East Side.”
Rose said the foundations on the two schools are different because the East Side site is flat, whereas the Joe Wright is not.
Wardell said the Joe Wright property has a 70-foot slope extending from the front of the property to the back.
Because of that slope, Rose said it was more cost effective to build a two-story structure and use a different type of foundation.
“It would be a huge expense to bring in a bunch of dirt to level it out rather than go to a different slab style,” he said.
Wardell said he and other officials from the district received bids last week for construction on the Fred Douglass and high school renovations.
“I don't have the list in front of me, but we got around 500 bids,” he said.
He said Pogue will go through the bids and will put together a guaranteed maximum price, hopefully to presented at the Jan. 23 school board meeting.
“If it is approved by the board, construction will start shortly after that.”
He said a little work has already been done at the high school, and personell are already excited.
“We actually started one piece of it over the holidays,” he said. “A new drive was poured on the east side of the campus.”
He said the drive on the south part of the campus will be blocked during part of the construction phase, and the new drive will provide an alternate route.
Local News
JISD: School construction projects remain on track to finish by August
- Local News
-
-
Agencies gearing up for Memorial Day weekend
The school year is wrapping up, and summer is almost here, but officials have some holiday safety tips to ensure the Memorial Day weekend is safe and fun for everyone.
-
Street blocked for sewer work
A portion of Bolton Street was blocked off Thursday as public works crews worked to find the source of a sewer stoppage.
-
Fourth-graders give scholarships, learn about college
As Tomato Fest approaches, officials with West Side Elementary school will have a booth to raise money for their West Side Elementary Alumni Scholarship given to graduating seniors.
-
Bullard council tables website decision
The Bullard city council tabled a decision on moving forward on a project for a new website design due to a lack of information.
-
LMC employees receive furlough notice
All but a core minimum group of Lon Morris employees received furlough notices Wednesday morning, and college President Miles McCall handed in his letter of resignation Tuesday, officials said Wednesday.
-
JISD alters graduation requirement for pair of subjects
Seniors at Jacksonville ISD will no longer have to take technology and health as a graduation requirement.
-
Rusk ISD lunch prices to rise 25 cents
A rise in school lunch prices is among several changes slated for Rusk ISD cafeterias.
-
County boasts 'pretty good' turnout
At the half-way mark of early voting for the May 29 primary, 1,485 Cherokee County voters turned in their ballots at the polls.
-
Organizations provide summer lunches for students
As schools approach summer vacation, Jacksonville has four locations offering free meals to students through the Summer Food Program.
-
Dome homes
Within the gated community of Lakewood in Cherokee County, homes are being built, ones so unique realtors can count how many they have seen on one hand.
- More Local News Headlines
-
Agencies gearing up for Memorial Day weekend